CORIUMNuclear Regulatory Intelligence
Live Data
CORIUM SCORING METHODOLOGY
Last updated: April 2026
HOW WE SCORE

Position on the circuit is determined by the furthest regulatory or deployment milestone a company has actually achieved. Document volume does not affect your score. A company with 1,000 filings that has not passed acceptance review is behind a company with 50 documents that holds a construction permit.

PHASE 1 — DESIGN & LICENSING (0–100 pts)

Most of the industry is here. Scoring is based on the furthest milestone reached, not cumulative points.

MilestonePointsDescription
Pre-Application Engagement5Company has begun informal NRC dialogue
Pre-Application Meeting Held15Formal pre-app meeting on record in ADAMS
Application Submitted25License application formally filed with NRC
Application Accepted for Review35NRC deemed application complete, review clock starts
Safety Review Active (RAIs Issued)50NRC actively issuing Requests for Additional Information
Draft Safety Evaluation Report65NRC issued draft SER — major milestone
Final Safety Evaluation Report80NRC issued final SER — near finish line
Design Certification / Approval90NRC approved the reactor design
Construction Permit Issued100Phase 1 complete — graduates to Phase 2
PHASE 2 — CONSTRUCTION (0–100 pts, separate circuit)

A company graduates to Phase 2 when it receives a construction permit. It appears on the Spa-Francorchamps circuit. A graduation marker remains on the Phase 1 circuit.

MilestonePointsDescription
Site Preparation Begun10Ground broken, site work started
Major Construction Started30Reactor building construction underway
Major Components Delivered60Reactor vessel, steam generators on site
Construction Complete90Ready for fuel load
Fuel Loaded100Phase 2 complete — graduates to Phase 3
PHASE 3 — OPERATIONS (0–100 pts, separate circuit)

Nobody has reached this phase yet. When a company achieves first criticality, their car appears on the Singapore Marina Bay circuit.

MilestonePointsDescription
First Criticality25Reactor goes critical for first time
Low Power Testing50Testing at reduced power levels
Full Power Operation80Operating at rated capacity
Commercial Operation100Race complete — reactor is commercially operating
MOMENTUM MODIFIER — ACTIVITY DECAY

Regulatory momentum matters as much as position. Companies with no significant NRC activity lose points over time. Only substantive filings count — administrative correspondence and routine meeting notices do not reset the clock.

InactivityPenalty
0–30 days without significant activity0 pts
30–90 days without significant activity−2 pts
90–180 days without significant activity−8 pts
180+ days without significant activity−20 pts
Official project pause announced−30 pts immediately

Score floor: a company cannot decay more than 25 points below its milestone anchor. Decay affects the score shown in standings but does not slide the car backwards on the circuit — circuit position reflects achieved milestones, not momentum.

FLAGS
⚑ YELLOW90+ days without significant NRC activity. Caution: momentum slowing.
⚑ RED180+ days inactive, or official project pause announced.
⚑ BLACKProject cancelled or license withdrawn. Car moves to retired section. Never deleted — remains as historical record.
DATA SOURCES
NRC ADAMS Public APIDocument data, updated daily
NRC Press ReleasesMilestone verification
DOE AnnouncementsGrant and program data
Company Press ReleasesFunding, partnerships
SEC FilingsPublic company data

All investor data is individually sourced and dated. We only publish what we can verify and cite.

LIMITATIONS

Corium is independent analysis. We are not affiliated with the NRC, DOE, or any company listed on this site. Data may be incomplete or become outdated.

Trust but verify. That is your job as an investor.

QUESTIONS OR CORRECTIONS?

If you spot an error or have better data, we want to know. hello@corium.io

← BACK TO THE RACE